Updated December 29, 2025
This project started on November 20, 2025, and was completed on December 24, 2025.
Completed

Updated December 29, 2025
This project started on November 20, 2025, and was completed on December 24, 2025.
There are twelve (12) total rural culvert improvements for this project (see “Schedule” section below for more details).
Construction began on November 20, 2025, with culvert lining and cleaning culverts on Bayou Gulch east of Fox Sparrow, Bayou Gulch west of Bayou Hills, Buckskin Lane at Lariat & two (2) culverts at Oak Hills Drive & Oakwood Lane.
From December 1 – 5, the Contractor cleaned the other seven (7) culverts located at Gold Camp & Placer, Corral & Sorrel, 5575 Lariat Dr, four (4) culverts on Happy Canyon between Lagae Rd Roundabout to just south of Castle Pines North Drive (Happy Canyon locations are shown on map above).