Starting at 7 a.m., Monday, April 6, Parker residents will notice an increase in construction activity as crews begin construction on the Pine Drive/Pine Lane Improvements Project. Improvements will be made on Pine Drive and Pine Lane, between Inspiration Drive and Lincoln Avenue, in Parker. View a map.
About the Project
This $13,218,000 project is fully funded by Douglas County and is scheduled to be completed in late summer 2027. The following project improvements will create a safer, more efficient Pine Drive/Pine Lane corridor:
- Increased roadway capacity by adding two additional lanes from north of Lincoln Avenue to north of Pine Lane, creating a total of four travel lanes (two in each direction).
- Improved mobility by installing traffic signals at the Ponderosa Drive/Pine Drive and Pine Lane/Pine Drive intersections.
- Reduced congestion by widening Pine Lane to include a through lane in each direction and a center turn lane, and providing a westbound right-turn deceleration lane at Dixon Drive/Pine Lane.
Hamon Infrastructure Co. was selected as the general contractor for this project.
Questions about construction or project progress? Call or email the project communications team, or visit the project website.
What are the impacts of this work?
As crews update the Pine Drive/Pine Lane corridor, travelers and residents should anticipate a variety of activities and impacts as construction progresses. Initial construction operations will require single lane closures and flagging operations, traffic shifts, and increased construction noise and truck traffic.
General construction hours will be in place Monday through Friday, 7 a.m. to 7 p.m. Saturday work may occur if approved by the Douglas County Engineer. There will be no construction activity on major holidays.
Xcel Gas Line Relocation
Xcel crews are relocating a gas line on Pine Lane. Motorists should watch for alternating single-lane traffic with flaggers. Please plan for delays up to 10 minutes while traveling through this area. Construction hours are:
- 7 p.m. to 7 a.m., Friday, April 3, and Saturday, April 4
- 8:30 a.m. to 3:30 p.m., Monday, April 6, through Friday, April 10
- 7 p.m. to 7 a.m., Saturday, April 11
Construction activities are weather and site-dependent and subject to change, which may impact the construction schedule.
Stay Informed
Your County. Your News. Get it first.
Be among the first to receive news as it happens. Subscribe to our online news push, and select your specific news focus and delivery preferences. Visit the Live Town Hall page and register for Town Hall notifications to ensure you are contacted to participate in future community conversations about topics important to you. Both services are free, and you can unsubscribe at any time. And don’t forget to follow Douglas County on Nextdoor, Facebook, Twitter, Instagram, LinkedIn and YouTube.